Exchange Datacenter Switchback


Generally, datacenter failures are either temporary or permanent. With a permanent failure, such as an event that has caused the permanent destruction of a primary datacenter, there’s no expectation that the primary datacenter will be activated. However, with a temporary failure (for example, an extended power loss or extensive but repairable damage), there’s an expectation that the primary datacenter will eventually be restored to full service.

The process of restoring service to a previously failed datacenter is referred to as a switchback. The steps used to perform a datacenter switchback are similar to the steps used to perform a datacenter switchover

It’s important that switchback not be performed until the infrastructure dependencies for Exchange have been reactivated, are functioning and stable, and have been validated. If these dependencies aren’t available or healthy, it’s likely that the switchback process will cause a longer than necessary outage, and the process could fail altogether.

Continue reading

Kemp Load Balancer


The KEMP LoadMaster combines versatility with ease-of-use to speed deployment of the complete portfolio of advanced messaging applications and protocols used by Exchange 2016 / 2013, including Outlook on the Web, MAPI/HTTP, Outlook Anywhere (OA), Exchange ActiveSync (EAS), Simple Mail Transfer Protocol (SMTP), Post Office Protocol version 3 (POP3), Internet Message Access Protocol version 4 (IMAP4) and Office Online Server (OOS). With built-in SSL acceleration and/or overlay, the LoadMaster offloads a key source of CPU drain to improve the capacity of the Exchange 2016 infrastructure. Layer 7 health checking at the LoadMaster ensures that if one of the Client Access components becomes inaccessible, the load balancer will take that component offline for that server, while automatically re-routing and reconnecting users to other functioning servers.

LoadMaster documentation is available at http://www.kemptechnologies.com/documentation.

Exchange Datacenter Switchover


A switchover is a manual process in which an administrator manually activates one or more mailbox database copies. Switchovers, which can occur at the database or server level, are typically performed as part of preparation for maintenance activities. Switchover management involves performing database or server switchovers as needed.

For example, if you need to perform maintenance on a Mailbox server in a DAG, you would first perform a server switchover so that the server didn’t host any active mailbox database copies.

There are four basic steps that you complete to perform a datacenter switchover, after making the initial decision to activate the second datacenter:

  1. Terminate a partially running datacenter
  2. Validate and confirm the prerequisites for the second datacenter
  3. Activate the Mailbox servers
  4. Activate the Client Access servers

Continue reading